The two EMS projects on Sein island and Ouessant island are EDF Store & Forecast’s first achievements in microgrid supply/demand balance management.
- Context: a 100% renewable production target for this non interconnected island
- Goal: to limit the use of genset
to compensate intermittency of PV production
…while ensuring quality and safety of the power system
- Project: genset (4.3 MW) + PV (45 kWp) + Marine gen. (->250 kW) + Li-ion Battery (1 MW–0,56 MWh)
- Status: commissioned in September 2017
More about Sein & Ouessant